Prepare your Odoo environment for Czech EET 2.0 by mapping how money is received, selecting an integration with documented compatibility, and testing the complete operating process before 1 January 2027. The official September announcement places the registration duty on that date. A working demonstration of one payment is insufficient: the real question is whether every relevant payment remains traceable when a cashier makes a correction, the connection fails or the server restarts.[2]

1. Establish the deadline and the evidence behind it

As checked on 14 October 2026, the official e-Sbírka record lists Act No. 180/2026 Sb., promulgated on 7 October 2026, with a principal effective date of 1 January 2027. EET 2.0 is therefore beyond the initial proposal stage.[1]

The current official timetable schedules DIS+ functions and certificate generation for 1 November and MOJE eet for 1 December 2026. It describes January as a pilot, but explicitly says this will already be standard registration. Treat those service dates as a published schedule and avoid interpreting “pilot” as permission to start preparing in February.[3]

Keep three separate entries in the project plan: the applicable legal obligation, the availability of government services, and your acceptance decision. Each needs an owner and evidence. A supplier release announcement answers a different question from a successful test in your deployed Odoo version. Where transitional treatment matters, have your tax adviser check the enacted wording and current guidance rather than relying on an older presentation.

2. Map payments, not just invoices or payment methods

Official guidance ties the scope to business income, contact or cash payments, and exceptions. Contact card and QR payments can be covered, while genuinely remote online payments and bank transfers are distinguished. A payment method label alone therefore cannot determine the result.[4]

There are exemptions linked to the taxpayer and others linked to particular activities. EET OFF is also a conditional arrangement for eligible natural persons in the flat-rate tax regime; it is not a general company exemption.[5][12]

Build an event register with finance and people who receive payments. For each flow, record the seller, channel, location, payment context, moment of receipt and evidence available to the system. Include money received outside Point of Sale: settlement at a service desk, a payment taken by a technician, and an invoice paid in person. Ask who can classify an unusual event and how that decision reaches the integration.

Separate the legal classification from the technical trigger. “Invoice posted” and “payment accepted” are different business events. A design that sends everything when an invoice is created can report the wrong moment or amount; a design limited to cash journals can miss relevant flows. Retain the reason for each inclusion or exclusion so a later channel change can be assessed without rediscovering the whole process.

3. Require fresh evidence for any existing EET module

The official interface specification, document version 1.2 dated 25 August 2026, identifies interface version 4.1. It explicitly describes the changes from the former 3.1 interface as incompatible. These are separate version numbers. The familiar EET name, SOAP transport or an old addon screenshot does not establish compatibility.[6]

Ask a proposed supplier to identify the exact addon build, supported Odoo version and edition, hosting requirements, interface revision and maintained dependencies. Request a list of supported business scenarios and explicit exclusions. An answer such as “supports Odoo” leaves too much unresolved: the same business process may cross custom code, payment-terminal software and an external cashier application.

If you already own legacy code, assess it as an engineering asset. Some structure or operational knowledge might be reusable, but budget for review, adaptation and retesting. Make maintenance ownership part of the decision: who follows official changes, how upgrades are released, and how a fault can be diagnosed without granting uncontrolled production access? No compatibility test by Odexer is claimed in this article.

4. Choose the integration boundary deliberately

The boundary should follow the system that reliably knows a payment has been accepted. Compare options against recovery and reconciliation work as well as initial implementation. The table is an architectural decision aid, not a claim that a particular product or connector already supplies these capabilities.

Questions for selecting an implementation approach
ApproachPotential advantageWhat you must prove
Integration in the Odoo payment flowDirect connection to the business recordSupported version, durable dispatch and behaviour during upgrades
Separate integration serviceOne place for several payment channelsClear ownership of each event, secure credentials and recoverable delivery
Existing external POS with Odoo integrationRetains the established cashier workflowWhich system reports, which imports, and how duplicate reporting is prevented
Separate manual workflowMay suit a very small, simple processAcceptable entry effort and a reliable reconciliation procedure

Avoid letting both Odoo and an external POS report the same payment independently. Conversely, avoid assuming that a terminal or fiscal service reports merely because it can process a card transaction. Put the responsibility in a short interface agreement: originating event, required identifiers, acknowledgement, correction path and the person responsible for unresolved exceptions.

5. Work through a realistic mixed-channel example

Consider a hypothetical Czech equipment retailer with a showroom, an online shop and a repair counter. For this design exercise, assume its adviser has classified the showroom and repair-counter payments as reportable and a defined remote prepaid order flow as outside scope. These are explicit example assumptions, not a classification of every retailer or every online order.

A customer orders online, changes the order at collection and pays an extra amount at the showroom. The proposed design retains the original order, the earlier payment and the new payment as separate linked events. It does not resend the whole order value simply because collection occurred. The scenario needs an agreed treatment for the additional amount and a test showing that the user cannot accidentally submit both events as one new receipt.

Now assume the customer returns one accessory after the cashier shift has closed. Test the refund as a new controlled operation, with permission checks and a link to the original sale in your own records. Reconciliation should explain the original receipt, the return and any difference in settlement timing. Do not erase history to make daily totals agree: an apparently tidy total can conceal a broken event trail.

6. Design a record that survives interruptions

Official guidance describes an acknowledgement containing the confirmation code POK. Distinguish that evidence from an attempted send or an error response. The data-field guidance also makes clear that verification mode is not fulfilment of the registration duty. A green connection test is therefore a different acceptance result from a registered transaction.[11][8]

A proposed integration should maintain explicit states such as prepared, awaiting response, confirmed and requiring review. Store enough evidence to connect the business event with the message and response. Design retries around the documented identity rules; generating a new business identity after every timeout risks converting an uncertain delivery into an additional transaction. Specify what happens if the application stops after sending but before saving the reply.

Keep the queue durable and observable. A dashboard should show the oldest unresolved event, not merely a count of failures. Assign an operator who can investigate a blocked message and an engineer who can repair the cause. A restart, database restore or failed deployment must have a recovery procedure that explains which events can safely be retried and which need reconciliation first.

7. Accept failure scenarios as carefully as successful sales

The official developer route includes documentation, test certificates and the Playground environment. Use these for an agreed acceptance programme, then separately check the production configuration and operational handover. The following tests are proposed acceptance criteria, not results already achieved by Odexer or any named connector.[7]

A minimum proposed acceptance matrix
ScenarioEvidence to request
Normal payment and split tenderCorrect event selection, amount and link to acknowledgement
Timeout after sendingRecovery without loss or an extra business event
Connection loss and application restartUnsent work persists and resumes with visible status
Refund or operator correctionAuthorised action, documented treatment and internal traceability
Two tills or two legal entitiesNo identifier collision or cross-company credential use
Certificate replacementControlled switch, restricted access and clear failure reporting
Daily reconciliationExplained differences between payments, submissions and accepted records

Run each case with a written expected result. Test operators should be able to tell whether a sale is complete, queued or blocked without reading technical logs. Include a deliberate configuration error to check that the system fails visibly. Record the exact software build and configuration with the results; a report from a different release is supporting context, not acceptance evidence for yours.

8. Make operations and security part of the scope

For an internet outage, official guidance requires sending without delay after connectivity returns, and no later than 48 hours from the sale. Use that outer limit to design alerts and escalation, not as a normal waiting period.[9]

Define internal warning thresholds early enough for someone to act during weekends and closing hours. Distinguish network failure, rejected content and missing permissions, since repeatedly sending the same invalid message does not repair its content. Keep an incident record with the affected interval, actions taken and reconciliation outcome. Support arrangements should name the systems covered and the contact path for each dependency.

Certificate installation is part of the official setup. Your implementation design should additionally define access to private keys, renewal ownership, revocation and recovery. Keep production credentials out of test databases and diagnostic exports. Limit logs to what is needed for investigation, and decide who can inspect transaction details. Operational convenience is not a reason for everyone supporting the ERP to share one unrestricted credential.[10]

9. Finish with a release decision, not an installation date

Start with a bounded assessment: payment-event register, exact software inventory, proposed integration boundary and unresolved tax questions. Convert it into a delivery backlog with named owners. Prioritise the flows that take money today; add planned channels explicitly instead of assuming future checkout changes will automatically inherit correct behaviour.

Before release, require approved scope, recorded test outcomes, certificate and environment checks, trained operators, reconciliation ownership and a recovery rehearsal. Agree a fallback process that finance has reviewed and staff can actually execute. After launch, review outstanding events and differences daily until the process is stable. The useful deliverable is a payment operation your team can explain and support, backed by evidence for the configuration you run.

Practical questions

Do we automatically need new till hardware?

Start with an inventory of the device, operating system, software and support status. Ask whether the chosen implementation can be deployed and maintained there, including secure certificate handling. Replace hardware because a documented requirement cannot be met, not merely because a new reporting obligation has a new name.

Can we stop issuing all customer documents?

The official announcement removes the obligation to issue and deliver a receipt specifically for EET 2.0. That does not establish that every other document requirement disappears. Review invoices, customer receipts and your service workflow separately with finance before changing the checkout experience.[2]

What should we request in an implementation proposal?

Request the supported configuration, payment scenarios, exclusions, acceptance evidence, ownership of updates and operational support boundaries. Ask for a priced scope built from those inputs. A connector name or a single success screenshot does not describe the work required to make your business process ready.

Sources and verification

Primary sources checked on 14 October 2026. Product behaviour still depends on the version, configuration and tested process.

  1. Zákon č. 180/2026 Sb., o evidenci tržeb a o změně některých dalších zákonů
    e-Sbírka, Ministerstvo vnitra ČR ·
  2. Prezident podepsal zákon o EET 2.0. Evidence tržeb startuje 1. ledna 2027
    Finanční správa ČR / Ministerstvo financí ČR ·
  3. Jaký je harmonogram EET 2.0?
    Finanční správa ČR / Ministerstvo financí ČR ·
  4. Kdo musí evidovat tržby?
    Finanční správa ČR / Ministerstvo financí ČR ·
  5. Co je z evidence tržeb vyjmuto?
    Finanční správa ČR / Ministerstvo financí ČR ·
  6. Elektronická evidence tržeb 2.0: popis datového rozhraní, verze 1.2
    Finanční správa ČR / Ministerstvo financí ČR ·
  7. Pro vývojáře
    Finanční správa ČR / Ministerstvo financí ČR ·
  8. Elektronická evidence tržeb: Popis položek datové zprávy s příklady jejich vyplnění, verze 1.0
    Finanční správa ČR / Ministerstvo financí ČR ·
  9. Chyby a jejich řešení
    Finanční správa ČR / Ministerstvo financí ČR ·
  10. Nastavení před zahájením evidence tržeb
    Finanční správa ČR / Ministerstvo financí ČR ·
  11. Evidence tržeb v praxi
    Finanční správa ČR / Ministerstvo financí ČR ·
  12. Co je režim EET OFF
    Finanční správa ČR / Ministerstvo financí ČR ·